SOFTWARE / INFRASTRUCTURE / SECURITY / KENYA
Done
Action completed
Field Notes Wireless Networking & ISP Solutions Wireless Network Planning Intermediate • 6 min read

How to plan a point-to-point wireless link

P Author: Peter Mwangi (Senior Network & Field Infrastructure Engineer)
Reviewed by: Lawrence Kamau (Lead Systems Architect & Infrastructure Engineer)
Published: May 1, 2026 • Last Updated: Nov 22, 2026 • Target Hardware: Cambium LINKPlanner and Ubiquiti ISP Design Center workflows.

Purpose: Validate path elevation profile, Fresnel clearance, antenna gain, rain fade margin, and Kenyan regulatory power limits before purchasing or climbing masts.

Reference Network Topology
Point-to-Point Layer-2 Bridge: Main Office -> Cambium/Ubiquiti PtP Radios -> Remote Branch Switch
NODE 01
Main Office Router & Switch
Gateway VLANs (VLAN 10 Mgmt, VLAN 20 Staff, VLAN 30 Voice)
NODE 02
Master Radio (AP PtP / TDD Master)
Cambium Force 300-25 or Ubiquiti PowerBeam 5AC (WDS Transparent Bridge)
NODE 03
5 GHz Outdoor RF Link (Clear Fresnel)
Aligned azimuth/elevation, shielded Cat6 + surge arrestors
NODE 04
Slave Radio (SM PtP / Station)
Remote building rooftop radio (Management IP on VLAN 10)
NODE 05
Remote Distribution Switch & UniFi APs
Trunk port carrying staff & management VLANs to branch desks

Prerequisites

  • Exact GPS coordinates (latitude/longitude) and proposed mast heights above ground for Site A and Site B.

Step-by-Step Configuration

STEP 01 — Plot Elevation Profile & Obstructions

Enter both coordinates into Cambium LINKPlanner or Ubiquiti ISP Design Center to inspect terrain elevation, building heights, and tree canopies along the path.

STEP 02 — Verify 60%+ First Fresnel Zone Clearance

Calculate the First Fresnel Zone radius at the midpoint and ensure mast heights clear terrain and trees by at least 60% of that radius.

STEP 03 — Select Dish Gain & Channel Width for Target Capacity

Match antenna gain (e.g., 19 dBi under 3 km, 25 dBi for 3–12 km) to maintain -52 to -58 dBm received signal with 25+ dB fade margin.

STEP 04 — Plan Power, Grounding & Regulatory Compliance

Specify UPS/solar autonomy, shielded Cat6 cabling, gas-discharge surge arrestors, and compliant Kenyan 5 GHz channel/EIRP settings.

Expected Results & Verification

An engineered link budget predicting modulation rate, expected TCP throughput, and 99.9%+ availability.

Troubleshooting Matrix

Issue:
Fix:
SECURITY HARDENING

Use narrow-beam directional dishes in urban Nairobi corridors to minimise off-axis interference and improve RF resilience.

BACKUP & RECOVERY

Archive the LINKPlanner / Design Center PDF report in the project folder.

P
Peter Mwangi Delight Engineering Team
Senior Network & Field Infrastructure Engineer
Specialization: Cambium ePMP, Ubiquiti airMAX, Fiber GPON / SFP+ Distribution & Tower Rigging

Leads physical wireless and optical deployments across Dagoretti South and greater Nairobi, specializing in interference mitigation and high-throughput point-to-point links.

Tested on Delight Living ISP Network (YouBroadband)
Nairobi NOC • Kabiria Road, Dagoretti South
Related Technical Guides
Was this engineering guide helpful?
Need professional installation, auditing, or troubleshooting? Request Network Consultation →